I'm new to OPC and having some issues with scheduling jobs in contention. The issue is that I have several jobs that are triggered online. These jobs can be triggered by a user at any time. The problem is how can I set it up in OPC in such a way that each job cannot run if at least one of the other jobs is running? |
|
Back to top |
|
|
enrico-sorichetti
Superior Member
Joined: 14 Mar 2007 Posts: 10891 Location: italy
|
|
|
|
use the special resources |
|
Back to top |
|
|
Terry Heinze
JCL Moderator
Joined: 14 Jul 2008 Posts: 1248 Location: Richfield, MN, USA
|
|
|
|
Is "special resources" similar to the "negative dependency" function of CA-7? |
|