Hi
I have three jobs JOB1, JOB2 and JOB3
My requirement is like if JOB1 gives RC 8 i dont want to execute JOB2 but JOB3 should be executed.
I fthe JOB1 gives a return code less than 8 i want to continue by executing JOB2 and JOB3
Kindly help me by providing a suggestion
Thanks and regards
Renjith |
|
| Back to top |
|
 |
arvind.m
Active User

Joined: 28 Aug 2008 Posts: 205 Location: Hyderabad
|
|
|
|
| If you are a programmer then you should talk to the operations people and let them create a scheduler event with the above requirement. It depends from shop to shop. |
|
| Back to top |
|
 |
expat
Global Moderator

Joined: 14 Mar 2007 Posts: 8798 Location: Welsh Wales
|
|
|
|
| Conditional execution of scheduler interface utilities or INTRDR steps to demand/trigger or submit the appropriate job. |
|