Hello everybody,

I have more than 30 years experience on mainframe from dos to Z/os and scheduled millions applications on it, including end-to-end.
Today on my new client, i arrive on a Z with OPC not configured as a server with unix but i have Unix servers separately with distributed TWS.
On both, the current plan start each day at 11:00 for a production start at 18:30.
When i try to schedule a standard TWS jobstream (monday till friday on workdays), on OPC it's perfect and on TWS Unix if it is before 00:00 all is okay, but if i want to schedule at 7:00 tomorrow, the result is that TWS schedule the jobstream on friday for saturday morning, and if i add freedays in the week with except don't run, it exactly runs on these freedays.
What it's strange is that i find no one example on the net about this nor on any brochure about this problem.
And what is totally extraordinary and against all logics is : if i think "MINUS 1" for everything : i schedule from sunday to thursday with saturday as free day and add freedays calendar with minus 1 free days : it's working perfectly ???
Is anyone has experienced this kind of UFO ???
Back to top
View user's profile Send private message
PeterHolland

Global Moderator


Joined: 27 Oct 2009
Posts: 2481
Location: Netherlands, Amstelveen

PostPosted: Mon Mar 13, 2017 2:43 pm
Reply with quote

As far as I remember an OPC connector has to be installed for communication between OPC-TWS.
Back to top
View user's profile Send private message
nsbl

New User


Joined: 16 Aug 2016
Posts: 2
Location: france

PostPosted: Mon Mar 27, 2017 11:31 pm
Reply with quote

Hi PeterHolland,

Thanks very much for your reply,
Yes, you are right, I worked at a customer with the connector,
And everything was planned from the Z, simply brilliant,
But we will not have it,
And I can not plan correctly on unix / tws,
Especially when I have somewhat complicated cycles,
It the reverse of what I ask,
That's why I tell the unix team,
That with the Z, I have a Rolls Royce in my hands,
We requested the assistance of an IBM consultant,
Thank you again for spending time on my question.
Back to top
View user's profile Send private message
PeterHolland

Global Moderator


Joined: 27 Oct 2009
Posts: 2481
Location: Netherlands, Amstelveen

PostPosted: Tue Mar 28, 2017 10:50 am
Reply with quote

nsbl. you are welcome.
Back to top
View user's profile Send private message
Harald.v.K

New User


Joined: 08 May 2009
Posts: 7
Location: Netherlands

PostPosted: Fri Apr 07, 2017 7:28 pm
Reply with quote

Hi nsbl,

I'm not as experienced as you, but from your description it seems to be an issue with a starting point, which is indexed 'zero' on the one platform, and indexed '1' on the other...

I was triggered by your 'minus 1' solution...
Back to top
View user's profile Send private message
View previous topic :: :: View next topic  
Post new topic   Reply to topic View Bookmarks
All times are GMT + 6 Hours
Forum Index -> IBM Tools

 


Similar Topics
Topic Forum Replies
No new posts first column truncated in search result IBM Tools 13
No new posts SDSF like solution in EJES (store com... All Other Mainframe Topics 4
No new posts executing XCTL command in COBOL witho... CICS 10
This topic is locked: you cannot edit posts or make replies. Need assistance in job scheduling logic. Mainframe Interview Questions 2
No new posts Job scheduling problem. JCL & VSAM 9
Search our Forums:

Back to Top