I have a mainframe job which is scheduled to run in Ca7 on every business day.
Step1 and Step2 should run as usual.
Step3 should verify the results of Step1 and Step2. In case of any problem Step4 should send a notification mail while Step5 should put this job on hold.
Successive steps should not run in case of a problem.
Once the results get verified manually, the operator will release the job.
Note: I don't want to schedule new job(s) for this task.
Please suggest. |
|
Back to top |
|
|
Anuj Dhawan
Superior Member
Joined: 22 Apr 2006 Posts: 6250 Location: Mumbai, India
|
|
|
|
Hi,
Why don't put "other" steps in a separate Job ? If any how you could put job on hold, later how would you remove the hold for further execution ? |
|
Back to top |
|
|
vikash singh
New User
Joined: 12 May 2007 Posts: 15 Location: noida
|
|
|
|
Thanks for prompt reply.
We have around 50 jobs in production which need this modification. Intoduction of 50 new jobs will be a big change.
If we put the jobs on hold then the support team will manually verify the result and then ask operation (Ca7 support) to release the job.
Any suggestions? |
|
Back to top |
|
|
dick scherrer
Moderator Emeritus
Joined: 23 Nov 2006 Posts: 19244 Location: Inside the Matrix
|
|
|
|
Hello,
Quote: |
Once the results get verified manually, the operator will release the job. |
Sorry, but this is nonsense. . . . For 1 job let alone 50 manual verifications and releases a day. . . Someone in management should have already put a stop to it. It wastes time and is quite error prone.
Suggest you work with the scheduling people and implement a proper solution using the scheduling tool you already have in place. |
|
Back to top |
|
|
vikash singh
New User
Joined: 12 May 2007 Posts: 15 Location: noida
|
|
|
|
Thank you.
I will look some alternate solution. |
|
Back to top |
|
|
dick scherrer
Moderator Emeritus
Joined: 23 Nov 2006 Posts: 19244 Location: Inside the Matrix
|
|
|
|
You're welcome - good luck
Someone will be here if there are questions.
d |
|
Back to top |
|
|
Anuj Dhawan
Superior Member
Joined: 22 Apr 2006 Posts: 6250 Location: Mumbai, India
|
|
|
|
vikash singh wrote: |
If we put the jobs on hold then the support team will manually verify the result and then ask operation (Ca7 support) to release the job. |
..and I thought we are living in 21st century..aarghh.. |
|
Back to top |
|
|
Robert Sample
Global Moderator
Joined: 06 Jun 2008 Posts: 8697 Location: Dubuque, Iowa, USA
|
|
|
|
Anuj, this sounds like a throwback to the 1960's or so .... |
|
Back to top |
|
|
enrico-sorichetti
Superior Member
Joined: 14 Mar 2007 Posts: 10873 Location: italy
|
|
|
|
I do not know about CA/7 but in TWS OPC the approach would be
to split the stream in 3 stages ( forgive the rough terminology )
a CPU stage, a manual/clerical stage( checking activity), again a CPU stage
the cpu stages are the usual stages for jcl
the manual stage is an activity whose completion is set by hand
( usually by some remote office ) after the checking and balances have proven being correct |
|
Back to top |
|
|
|