Hi All,
Is it possible to change parameter values dynamically in a JCL without human intervenction?
Can the job scheduler do date arithmetic to determine the value that it needs to dynamically included in the JCL? |
|
Back to top |
|
|
superk
Global Moderator
Joined: 26 Apr 2004 Posts: 4652 Location: Raleigh, NC, USA
|
|
|
|
Yes, absolutely. |
|
Back to top |
|
|
reshmamohiyiddin
New User
Joined: 26 Jun 2008 Posts: 2 Location: Richmond
|
|
|
|
Thanks Kevin. Do you mean to say this can be acheived only with the help of ReXX?
Thanks
Reshma |
|
Back to top |
|
|
superk
Global Moderator
Joined: 26 Apr 2004 Posts: 4652 Location: Raleigh, NC, USA
|
|
|
|
Well, you haven't as of yet mentioned what job scheduling system you're using. Most likely, though, yes, the scheduling system would need this process to be coded in REXX. |
|