Dear Expert:
I have 2 jobs A and B. Job B triggers on successful completion of Job A (RC=4).
When job A is forced complete, job B trigger automatically.
I do not want Job B to trigger when job A is forced complete. I would want job B to trigger only when job A completes successfully.
How can I stop this?
Thanks in advance.
Regards
Supernuvo
Control-M : Do not trigger dependent job upon force complete
-