I have a job which needs to run on last day of every month even the calendar is off for that day. I used ROLL:N option and below options in setting up the job.
__ X __MONTHLY JAN: X FEB: X MAR: X APR: X MAY: X JUN: X
JUL: X AUG: X SEP: X OCT: X NOV: X DEC: X
WEEK: /-0 DAY-OF-WEEK:
RDAY: -0
But schedule is not setting up for all month's last day. I am not able to figure out what is could be the problem is.
Can some one help me in this? |
|
Back to top |
|
|
alan_blore
New User
Joined: 01 Aug 2007 Posts: 50 Location: Hosur
|
|
|
|
Hi Surya,
Which CA Scheduler product are you talking about here.
CA has ESP, CA-7, CA-Scheduler....
Thanks! |
|