OPC scheduler - Question


IBM Mainframe Forums -> IBM Tools
Post new topic   Reply to topic
View previous topic :: View next topic  
Author Message
rukmakiran

New User


Joined: 19 Apr 2005
Posts: 21

PostPosted: Wed Apr 28, 2010 2:51 am
Reply with quote

Does any one let me know how to setup the OPC application /JObs as a time dependent ? Like some of the JOBs should run based on the particular time frame and also with predecessors.

Thanks ,
Rukma.
Back to top
View user's profile Send private message
expat

Global Moderator


Joined: 14 Mar 2007
Posts: 8797
Location: Welsh Wales

PostPosted: Wed Apr 28, 2010 11:27 am
Reply with quote

The answer is in the manual(s).

These are readily available from the IBM website if your peers do not know, or will not tell you where your site copies are.
Back to top
View user's profile Send private message
rukmakiran

New User


Joined: 19 Apr 2005
Posts: 21

PostPosted: Thu Apr 29, 2010 9:23 am
Reply with quote

Appreciate if you cold you locate me the same from the IBM manuals ?

Thanks,
Back to top
View user's profile Send private message
dbzTHEdinosauer

Global Moderator


Joined: 20 Oct 2006
Posts: 6966
Location: porcelain throne

PostPosted: Thu Apr 29, 2010 3:57 pm
Reply with quote

Here is a link to IBM Redbooks for OPC

apparently, OPC is part of TIVOLI,
which means you can go to the IBM LIbrary Server Library
and enter TIVOLI as a search argument.

you should bookmark both these sites,
they are the path to your manuals in the future.
Back to top
View user's profile Send private message
rukmakiran

New User


Joined: 19 Apr 2005
Posts: 21

PostPosted: Thu Apr 29, 2010 11:47 pm
Reply with quote

Thanks for details for showing the location for finding the document ,
But want to know where the topic located in the Tivoli/OPC document - which explains the options to schedule a job with the predecessor & also the time dependent (like for example i need a XYZ job to run at 3:00P even though the predecessor was successfully completed at 1:00P )

Appreciate if you could get me those details ??
Back to top
View user's profile Send private message
dick scherrer

Moderator Emeritus


Joined: 23 Nov 2006
Posts: 19244
Location: Inside the Matrix

PostPosted: Fri Apr 30, 2010 12:54 am
Reply with quote

Hello,

Click on the IBM Library Server Library link above and enter tivoli workload as the "find" criteria.

From the returned list, look thru/search the documentation for your release of the product.
Back to top
View user's profile Send private message
P.RAJESH
Currently Banned

New User


Joined: 20 Mar 2008
Posts: 54
Location: chennai

PostPosted: Fri Apr 30, 2010 10:43 am
Reply with quote

Hi rukmakiran,

I'm assuming that you are from scheduling team based on that I'm writting the below points.

1. While creating the jobs inside a application make the jobs as time dependent by below options in OPC that

Code:
4 AUTOMATIC OPTIONS   - Job, WTO, and print options


In Automatic options will have jobs release options shown below,

Code:
ob release options:         
 Submit                : Yes 
 Hold/release          : Yes 
 Time dependent        :  YES   
 Suppress if late      : No   


Time dependent YES indicates that job is Time dependent.

Code:
6 TIME                - Time specifications 


Time specifications specifies when the job to run.

hope this helps.
Back to top
View user's profile Send private message
rukmakiran

New User


Joined: 19 Apr 2005
Posts: 21

PostPosted: Sat May 01, 2010 1:30 am
Reply with quote

Thank you very much Rajesh, for the detailed information what i needed.
i am not from scheduling but having access to OPC to schedule our Jobs.
Back to top
View user's profile Send private message
P.RAJESH
Currently Banned

New User


Joined: 20 Mar 2008
Posts: 54
Location: chennai

PostPosted: Mon May 03, 2010 9:19 am
Reply with quote

Hi rukmakiran,

It was better choice to talk with your scheduling team.

I think you are having access only for monitoring not to update any application in OPC data base.
Back to top
View user's profile Send private message
View previous topic :: :: View next topic  
Post new topic   Reply to topic View Bookmarks
All times are GMT + 6 Hours
Forum Index -> IBM Tools

 


Similar Topics
Topic Forum Replies
No new posts Question for file manager IBM Tools 7
No new posts OPCP scheduler questio IBM Tools 0
No new posts question for Pedro TSO/ISPF 2
No new posts How can I select certain file dependi... JCL & VSAM 12
This topic is locked: you cannot edit posts or make replies. How can I select certain file dependi... Compuware & Other Tools 1
Search our Forums: