I have a problem where I have batch programs on two different CICs regions sending 500,000 messages each (total 1M+) to my DB2 row creator program running on another CICS region.
The Q between is MQ and is setup with Priority, the default is 5 and the batch messages are setup with this(or setup with -1 in the pgm), but I also have online messages being sent to the Q with priority of 9.
But on some days(once every week) we are seeing the Rows for the online transactions being created a few hours later when the 1 million other transactions have been processed does anyone know if MQ has a Q limit.
I don't have alot of knowledge on MQ so any help would be great.
Thanks allan |
|
Back to top |
|
|
allh2k
New User
Joined: 31 Jan 2008 Posts: 7 Location: warrington
|
|
|
|
Please ignore problem has been resolved |
|
Back to top |
|
|
dbzTHEdinosauer
Global Moderator
Joined: 20 Oct 2006 Posts: 6966 Location: porcelain throne
|
|
|
|
have you solved this problem?
Quote: |
I don't have alot of knowledge on MQ |
|
|
Back to top |
|
|
PeterHolland
Global Moderator
Joined: 27 Oct 2009 Posts: 2481 Location: Netherlands, Amstelveen
|
|
|
|
allh2k wrote: |
Please ignore problem has been resolved |
How? |
|
Back to top |
|
|
allh2k
New User
Joined: 31 Jan 2008 Posts: 7 Location: warrington
|
|
|
|
Sorrry for the vvvvv late reply but the program was using data from a third party program that was not being populated as designed a new solution using different data was coded.
Works perfectly now with priorities from 1 to 9. |
|