Hi,
We are running a BMP IMS program from a JCL. We have scheduled the PSB into the test environment before running the job.
The job failed with U0428 code, and the explanation is that " the PSB is not defined during the IMS definition". The PSB is available in the TEST PSBLIB and it was scheduled properly into the correct test set.
Did any one face this problem earlier, and can any one provide a solution to this problem. |
|
Back to top |
|
|
t5590ag
Active User
Joined: 21 May 2009 Posts: 139 Location: United States
|
|
|
|
arun u can just go and check the psb status in ur online test ims region. might be stopped or locked but that gives 456 as far as i know..just fyi.. |
|
Back to top |
|
|
t5590ag
Active User
Joined: 21 May 2009 Posts: 139 Location: United States
|
|
|
|
arun ..one more thing..it depends on system..before u use psb u shud get it in prod lib..not in test...get it approved .. |
|
Back to top |
|
|
dick scherrer
Moderator Emeritus
Joined: 23 Nov 2006 Posts: 19244 Location: Inside the Matrix
|
|
|
|
Hello,
Quote: |
I have not understood, what is difference between using prod and test library. |
Suggest you speak with your manager, some senior, or your dba.
One of the most basic controls is that Production jobs are run from Production libraries. Developers should not modify Production libraries (or data for that matter) "on the fly".
Developers should run their tests using the test libraries for their code to be tested and possibly read production libraries to execute already existing production modules.
How production and test libraries as well as production/test files and databases are managed should be learned from those people i mentioned above. |
|
Back to top |
|
|
enrico-sorichetti
Superior Member
Joined: 14 Mar 2007 Posts: 10872 Location: italy
|
|
|
|
Hi Dick!
I just deleted the post You were referring because the gentleman had already started another thread on the same issue
sorry for the inconvenience
as usual people ask on the forums how to solve issues that should be discussed with their support |
|
Back to top |
|
|
dick scherrer
Moderator Emeritus
Joined: 23 Nov 2006 Posts: 19244 Location: Inside the Matrix
|
|
|
|
Hi Enrico,
Yup, i tagged this bit onto the other topic
i suppose later i'll do some cleanup
It is 2a.m. and i'll be away for a while. . .
d |
|
Back to top |
|
|
enrico-sorichetti
Superior Member
Joined: 14 Mar 2007 Posts: 10872 Location: italy
|
|
|
|
Hi Dick!
have a good sleep
it' s 9 AM here |
|
Back to top |
|
|
t5590ag
Active User
Joined: 21 May 2009 Posts: 139 Location: United States
|
|
|
|
hii dick, just wanted to discuss this..in my system if am writing a new code I first have to get PSB done and once we get approvals it can be used both in test and prod. hence both prod and test psblibs have same content, just we address them differently. |
|
Back to top |
|
|
mkarthikeyan
New User
Joined: 07 Aug 2008 Posts: 34 Location: Bangalore
|
|
|
|
For DLI, Generate the PSB to HLQ.PSBLIB and this library(PDS) must be defined in APF( Authorized program facility) to use it
For BMP, same like DLI but define the PSB to IMS system using APPLCTN macro. Incase of BMP, IMS schedules the PSB when you submit the BMP job.
For Online(MPP), IMS schedules the PSB when the transaction is involved.
Transaction is defined to using TRANSACT macro. The PSB name and program has to be same
Thanks
Karthik |
|
Back to top |
|
|
dick scherrer
Moderator Emeritus
Joined: 23 Nov 2006 Posts: 19244 Location: Inside the Matrix
|
|
|
|
Hello,
It is good to see another who will reply to ims topics
Please note though this topic was over 3 years old.
It is best to reply to currently active topics rather than those that have been dormant for years. |
|
Back to top |
|
|
|