I apologise for posting this in another forum by mistake.
Can anybody please clarify for me when exactly OPC 'freezes' the version of JCL that it will submit for a Job? I know, for instance, that you can edit the JCL within the Current Plan, so this is obviously stored somewhere. I also know that if a Job ends in error, the same version of the JCL will be submitted when Rerun is used.
Critical question: If I change the JCL in the Job Library after the Current Plan has been built, will the new version be run or the old?
Thanks for any helpful replies.
Pat |
|
Back to top |
|
|
LukeZhang
New User
Joined: 29 May 2006 Posts: 1 Location: Shanghai China
|
|
|
|
After the job be pulled out in CP, if you change JCL in your lib, the job in OPC can not be updated.
You can ask some team to refresh your JCL in CP with the new version. Or you can request to ADHOC RUN the latest job. |
|
Back to top |
|
|
MCEVOY
New User
Joined: 21 Nov 2005 Posts: 18
|
|
|
|
Thank you for helpful reply, but that is not what I see happening.
I looked in CP, saw incorrect JCL, changed Job in library, looked again in CP and the new JCL was now showing (and ran that night).
I didn't think it worked like that, hence my question. |
|
Back to top |
|
|
|